Module 10 · Lesson 17 of 18

Supplier quality improvement

← Back to moduleBack to academy

Learning objectives

  • Define supplier CTQs and the correct denominator per material family.
  • Rank suppliers on like-for-like PPM, capability, delivery and response.
  • Design supplier development that prevents defects, not just inspects them.

Problem and CTQ

Incoming fabric, trims, chemicals and service performance drive defects, delay and variability. Ranking suppliers requires like-for-like materials and validated data.

DMAIC path

  • Define supplier CTQs and denominator.
  • Validate incoming and use-stage data and traceability.
  • Stratify supplier/item/lot/time; compare PPM, capability, delivery and response.
  • Confirm causes jointly with the supplier.

Improvement choices

  • Clear specifications and measurement method.
  • Sample approval and process capability plan.
  • Corrective action, early-warning data and supplier development.

Control plan

  • Supplier PPM, lot acceptance, on-time delivery, SCAR closure and effectiveness, repeat issue, line disruption and total cost.

Garment-factory example

Two twill suppliers run at PPM 5,200 and PPM 8,900 on shade delta; deeper look shows the second supplies a stripe fabric with stricter matching. Comparing only plain fabric lots, the two suppliers are within 300 PPM of each other, and the joint action shifts to matching tolerance.

Common mistakes

  • Ranking unlike materials on raw counts.
  • Relying on incoming inspection instead of supplier process control.

Knowledge check

Pick one answer per question. Explanations appear after you submit.

  1. 1. A fair supplier PPM comparison requires:

  2. 2. Sustainable supplier improvement comes primarily from:

Author: Sanjeewa Dehiwalage · Last reviewed: 2026-07-21

Stay in touch

New chapters, delivered quietly.

A short note when a new story, reflection or milestone is added. No noise, no spam — unsubscribe with a single click.