Module 10 · Lesson 16 of 18

Energy, water, and material-waste improvement

← Back to moduleBack to academy

Learning objectives

  • Define resource-use KPIs per good garment (kWh, litres, grams).
  • Map high-use steps and stratify by machine, recipe and load.
  • Improve utilities without compromising quality, safety or compliance.

Problem and CTQ

Resource use per good garment is often excessive while product quality, safety and compliance must remain protected. Normalize every KPI by good output and product mix.

DMAIC path

  • Define boundary and baseline; validate meters and material balance.
  • Map high-use steps; stratify by machine, recipe, load, leak, idle and rework.
  • Never claim reductions caused by lower volume.

Improvement choices

  • Leak and idle control; load optimization.
  • Recipe/process redesign; heat/water recovery.
  • Right-first-time and reuse/recycling with risk approval.

Control plan

  • kWh/garment, water litres/garment, chemical grams/garment, waste kg/garment; cost, quality and compliance guardrails.

Garment-factory example

A dye-house cuts water from 82 to 61 L/kg through load standardization and rinse optimization while shade pass % improves 2.4 points and MRSL compliance is unaffected.

Common mistakes

  • Claiming a per-garment reduction that is really volume mix.
  • Reusing water without a documented chemical-risk approval.

Knowledge check

Pick one answer per question. Explanations appear after you submit.

  1. 1. Utility KPIs must be normalized by:

  2. 2. Water reuse in wet processing requires:

Author: Sanjeewa Dehiwalage · Last reviewed: 2026-07-21

Stay in touch

New chapters, delivered quietly.

A short note when a new story, reflection or milestone is added. No noise, no spam — unsubscribe with a single click.