Module 10 · Lesson 11 of 18
Machine downtime and OEE improvement
Learning objectives
- Compute OEE with honest ideal cycle and good count.
- Separate availability, performance and quality losses.
- Focus improvement on the constraint machine, not every machine.
Problem and CTQ
OEE = availability × performance × quality. Equipment losses reduce capacity and disrupt flow, but only losses at the constraint move throughput.
DMAIC path
- Define planned time and loss codes.
- Validate timestamps, ideal rate and good count.
- Pareto breakdown, minor stops, speed loss, setup and defects; compute MTBF and MTTR.
Improvement choices
- Autonomous and planned maintenance.
- Critical spares, centerlining, response escalation and condition checks.
- Failure-mode actions on repeat causes.
Control plan
- OEE and its three factors, downtime minutes, MTBF, MTTR, repeat failure, schedule compliance and throughput at the constraint.
Garment-factory example
A bar-tack machine at the constraint runs at 58% OEE (Availability 82%, Performance 88%, Quality 80%). A 30-minute daily condition check plus a spare-parts kit lifts OEE to 74% and adds 210 shirts/day at the same line count.
Common mistakes
- Using OEE to judge operators.
- Inflating the ideal cycle to make OEE look worse (or better).
Knowledge check
Pick one answer per question. Explanations appear after you submit.
1. OEE at 90% for a non-constraint machine means:
2. The correct ideal cycle is: