Module 4 · Lesson 5 of 22
Cause-and-effect matrix
Learning objectives
- Weight CTQ outputs against process inputs.
- Score relationships consistently across the team.
- Select the vital few Xs for validation.
Prioritising Xs
- List CTQ outputs with weights (1–10).
- List process steps and inputs from the detailed map.
- Score relationships with 0/1/3/9.
- Sum weighted scores; sensitivity-check the top Xs.
Garment-factory example
For collar appearance, folder setting, seam allowance, operator handling, feed balance and material stretch are scored against symmetry, puckering, dimension and strength; the top three Xs feed the data plan.
Method
- Confirm CTQs and weights with the sponsor.
- Calibrate scoring definitions before rating.
- Score cross-functionally and reconcile outliers.
- Plan data collection for the top Xs.
Common mistakes
- Treating scores as measured effects.
- Letting one manager set all scores.
Knowledge check
Pick one answer per question. Explanations appear after you submit.
1. The C&E matrix output is best used as:
2. Scoring is safer when:
Author: Sanjeewa Dehiwalage · Last reviewed: 2026-07-21