Module 10 · Lesson 4 of 18

Sewing-line efficiency improvement

← Back to moduleBack to academy

Learning objectives

  • Calculate sewing-line efficiency correctly and honestly.
  • Separate operator, method and machine causes of low efficiency.
  • Design a short intervention that raises efficiency without hurting quality.

The efficiency equation

Sewing-line efficiency = (Standard minutes produced ÷ Total minutes worked) × 100. Standard minutes come from the operation bulletin. Total minutes worked include every operator on the line for the same clock period.

What efficiency does not tell you

  • It does not distinguish poor method from poor operator skill.
  • It hides quality problems if reworked pieces are counted as output.
  • It reacts slowly to bottleneck moves within the line.

Garment-factory example

A polo line produces 800 shirts at an SMV of 12.5 minutes with 30 operators working 480 minutes. Standard minutes produced = 800 × 12.5 = 10,000. Total worked = 30 × 480 = 14,400. Efficiency = 10,000 ÷ 14,400 = 69.4%. A 3-week intervention that adds a sleeve-attach folder and rebalances two operations raises efficiency to 78% while DHU drops from 12 to 7.

Method

  1. Confirm the SMV before quoting efficiency; a wrong SMV wrecks the ratio.
  2. Report efficiency together with DHU so quality cannot silently drop.
  3. Time only the current bottleneck for the fastest gain.

Common mistakes

  • Counting reworked pieces in the output.
  • Chasing 100% efficiency and letting quality slip.

Knowledge check

Pick one answer per question. Explanations appear after you submit.

  1. 1. 800 shirts at SMV 12.5 with 30 operators × 480 minutes. Efficiency is:

  2. 2. Why report DHU alongside efficiency?

Author: Sanjeewa Dehiwalage · Last reviewed: 2026-07-21