Module 14: Planning and Agility

Activity 9 of 11

Practical brief

Bangla is being improved for factory-floor accuracy and native wording. It will return once the review is complete. English is available now.

Use this 24-hour replanning checklist whenever a critical input is delayed:

Confirm the delay: get the revised arrival date in writing from the supplier or freight forwarder.

Map the new critical path: mark every operation that now touches the shipment date.

Build two scenarios: one with no extra cost and one with airfreight or overtime.

Calculate total cost per scenario, including penalties, margin and relationship risk.

Present a recommendation to the buyer before the end of the same business day.

Assign owners for each recovery action and set a check-in time within 24 hours.